The landslide that occurred on October 25, which caused a train to derail, caused significant damage to the Cévennes railway line, between Génolhac, in the Gard, and Villefort, in Lozère. Currently, the clearing work is continuing and should be completed by the end of the year, SNCF indicates in a press release. In total, nearly 2,000 m3 of earth and rocks will have been removed.
After this first stage, a retaining structure will have to be rebuilt to ensure the stability of the slope and the departmental road. Complex work, continues the SNCF, requiring surveys and data acquisitions in order to define the type of reinforcement to be favored. In addition, track renewal work will be undertaken in the area impacted by the landslide.
In the end, it is indicated that “given the nature of the numerous operations to be carried out and the particularly difficult conditions of access to the site, several months of work will be necessary. Rail traffic will resume on April 25, 2025.”