Workers are busy on the top of the Mende road. MIDI LIBRE – Y. PO.
The section between the Girac roundabout and the city center is well advanced compared to the western part still under construction.
The northern part of the tramway line 5 construction site is progressing very well. We are even witnessing the very last rail welds on this sector between the Girac roundabout (Clapiers) and the connection with line 1 in the city center.
200% Deposit Bonus up to €3,000 180% First Deposit Bonus up to $20,000New stations have even been installed on this section, which is much more advanced than the western part (between the Genneveaux roundabout and Saint-Denis). For the latter, there is still major work to be done on the Lavérune road, where many workers are busy, despite the bad weather.
On the western part, almost all the rails are connected. This is the sector that should host the first tests of the new trains in July.
This Friday, January 24, a storm named Eowyn will hit the west coast of France,…
Les policiers ont d'abord tenté de le maîtriser avec l'aide d'un taser, sans succès. ENVATO…
L'essentiel de l'information en région chaque soir sur Midilibre.fr Midi Libre et MAXPPP Chaque soir…
This Friday, January 24, a storm named Eowyn will hit the west coast of France,…
Skiers go up to 150 km/h. XinHua - He Canling After a series of accidents…
Rodez avait terminé 4e de de la Ligue 2 en 2024 sous les ordres de…